項目管理之路三(doc)
綜合能力考核表詳細內(nèi)容
項目管理之路三(doc)
11. Advanced Scheduling Techniques
11.1 Use of Advanced Scheduling Techniques
Construction project scheduling is a topic that has received extensive research over a number of decades. The previous chapter described the fundamental scheduling techniques widely used and supported by numerous commercial scheduling systems. A variety of special techniques have also been developed to address specific circumstances or problems. With the availability of more powerful computers and software, the use of advanced scheduling techniques is becoming easier and of greater relevance to practice. In this chapter, we survey some of the techniques that can be employed in this regard. These techniques address some important practical problems, such as:
• scheduling in the face of uncertain estimates on activity durations,
• integrated planning of scheduling and resource allocation,
• scheduling in unstructured or poorly formulated circumstances.
A final section in the chapter describes some possible improvements in the project scheduling process. In Chapter 14, we consider issues of computer based implementation of scheduling procedures, particularly in the context of integrating scheduling with other project management procedures.
Back to top
11.2 Scheduling with Uncertain Durations
Section 10.3 described the application of critical path scheduling for the situation in which activity durations are fixed and known. Unfortunately, activity durations are estimates of the actual time required, and there is liable to be a significant amount of uncertainty associated with the actual durations. During the preliminary planning stages for a project, the uncertainty in activity durations is particularly large since the scope and obstacles to the project are still undefined. Activities that are outside of the control of the owner are likely to be more uncertain. For example, the time required to gain regulatory approval for projects may vary tremendously. Other external events such as adverse weather, trench collapses, or labor strikes make duration estimates particularly uncertain.
Two simple approaches to dealing with the uncertainty in activity durations warrant some discussion before introducing more formal scheduling procedures to deal with uncertainty. First, the uncertainty in activity durations may simply be ignored and scheduling done using the expected or most likely time duration for each activity. Since only one duration estimate needs to be made for each activity, this approach reduces the required work in setting up the original schedule. Formal methods of introducing uncertainty into the scheduling process require more work and assumptions. While this simple approach might be defended, it has two drawbacks. First, the use of expected activity durations typically results in overly optimistic schedules for completion; a numerical example of this optimism appears below. Second, the use of single activity durations often produces a rigid, inflexible mindset on the part of schedulers. As field managers appreciate, activity durations vary considerable and can be influenced by good leadership and close attention. As a result, field managers may loose confidence in the realism of a schedule based upon fixed activity durations. Clearly, the use of fixed activity durations in setting up a schedule makes a continual process of monitoring and updating the schedule in light of actual experience imperative. Otherwise, the project schedule is rapidly outdated.
A second simple approach to incorporation uncertainty also deserves mention. Many managers recognize that the use of expected durations may result in overly optimistic schedules, so they include a contingency allowance in their estimate of activity durations. For example, an activity with an expected duration of two days might be scheduled for a period of 2.2 days, including a ten percent contingency. Systematic application of this contingency would result in a ten percent increase in the expected time to complete the project. While the use of this rule-of-thumb or heuristic contingency factor can result in more accurate schedules, it is likely that formal scheduling methods that incorporate uncertainty more formally are useful as a means of obtaining greater accuracy or in understanding the effects of activity delays.
The most common formal approach to incorporate uncertainty in the scheduling process is to apply the critical path scheduling process (as described in Section 10.3) and then analyze the results from a probabilistic perspective. This process is usually referred to as the PERT scheduling or evaluation method. [1] As noted earlier, the duration of the critical path represents the minimum time required to complete the project. Using expected activity durations and critical path scheduling, a critical path of activities can be identified. This critical path is then used to analyze the duration of the project incorporating the uncertainty of the activity durations along the critical path. The expected project duration is equal to the sum of the expected durations of the activities along the critical path. Assuming that activity durations are independent random variables, the variance or variation in the duration of this critical path is calculated as the sum of the variances along the critical path. With the mean and variance of the identified critical path known, the distribution of activity durations can also be computed.
The mean and variance for each activity duration are typically computed from estimates of "optimistic" (ai,j), "most likely" (mi,j), and "pessimistic" (bi,j) activity durations using the formulas:
(11.1)
項目管理之路三(doc)
11. Advanced Scheduling Techniques
11.1 Use of Advanced Scheduling Techniques
Construction project scheduling is a topic that has received extensive research over a number of decades. The previous chapter described the fundamental scheduling techniques widely used and supported by numerous commercial scheduling systems. A variety of special techniques have also been developed to address specific circumstances or problems. With the availability of more powerful computers and software, the use of advanced scheduling techniques is becoming easier and of greater relevance to practice. In this chapter, we survey some of the techniques that can be employed in this regard. These techniques address some important practical problems, such as:
• scheduling in the face of uncertain estimates on activity durations,
• integrated planning of scheduling and resource allocation,
• scheduling in unstructured or poorly formulated circumstances.
A final section in the chapter describes some possible improvements in the project scheduling process. In Chapter 14, we consider issues of computer based implementation of scheduling procedures, particularly in the context of integrating scheduling with other project management procedures.
Back to top
11.2 Scheduling with Uncertain Durations
Section 10.3 described the application of critical path scheduling for the situation in which activity durations are fixed and known. Unfortunately, activity durations are estimates of the actual time required, and there is liable to be a significant amount of uncertainty associated with the actual durations. During the preliminary planning stages for a project, the uncertainty in activity durations is particularly large since the scope and obstacles to the project are still undefined. Activities that are outside of the control of the owner are likely to be more uncertain. For example, the time required to gain regulatory approval for projects may vary tremendously. Other external events such as adverse weather, trench collapses, or labor strikes make duration estimates particularly uncertain.
Two simple approaches to dealing with the uncertainty in activity durations warrant some discussion before introducing more formal scheduling procedures to deal with uncertainty. First, the uncertainty in activity durations may simply be ignored and scheduling done using the expected or most likely time duration for each activity. Since only one duration estimate needs to be made for each activity, this approach reduces the required work in setting up the original schedule. Formal methods of introducing uncertainty into the scheduling process require more work and assumptions. While this simple approach might be defended, it has two drawbacks. First, the use of expected activity durations typically results in overly optimistic schedules for completion; a numerical example of this optimism appears below. Second, the use of single activity durations often produces a rigid, inflexible mindset on the part of schedulers. As field managers appreciate, activity durations vary considerable and can be influenced by good leadership and close attention. As a result, field managers may loose confidence in the realism of a schedule based upon fixed activity durations. Clearly, the use of fixed activity durations in setting up a schedule makes a continual process of monitoring and updating the schedule in light of actual experience imperative. Otherwise, the project schedule is rapidly outdated.
A second simple approach to incorporation uncertainty also deserves mention. Many managers recognize that the use of expected durations may result in overly optimistic schedules, so they include a contingency allowance in their estimate of activity durations. For example, an activity with an expected duration of two days might be scheduled for a period of 2.2 days, including a ten percent contingency. Systematic application of this contingency would result in a ten percent increase in the expected time to complete the project. While the use of this rule-of-thumb or heuristic contingency factor can result in more accurate schedules, it is likely that formal scheduling methods that incorporate uncertainty more formally are useful as a means of obtaining greater accuracy or in understanding the effects of activity delays.
The most common formal approach to incorporate uncertainty in the scheduling process is to apply the critical path scheduling process (as described in Section 10.3) and then analyze the results from a probabilistic perspective. This process is usually referred to as the PERT scheduling or evaluation method. [1] As noted earlier, the duration of the critical path represents the minimum time required to complete the project. Using expected activity durations and critical path scheduling, a critical path of activities can be identified. This critical path is then used to analyze the duration of the project incorporating the uncertainty of the activity durations along the critical path. The expected project duration is equal to the sum of the expected durations of the activities along the critical path. Assuming that activity durations are independent random variables, the variance or variation in the duration of this critical path is calculated as the sum of the variances along the critical path. With the mean and variance of the identified critical path known, the distribution of activity durations can also be computed.
The mean and variance for each activity duration are typically computed from estimates of "optimistic" (ai,j), "most likely" (mi,j), and "pessimistic" (bi,j) activity durations using the formulas:
(11.1)
項目管理之路三(doc)
[下載聲明]
1.本站的所有資料均為資料作者提供和網(wǎng)友推薦收集整理而來,僅供學習和研究交流使用。如有侵犯到您版權的,請來電指出,本站將立即改正。電話:010-82593357。
2、訪問管理資源網(wǎng)的用戶必須明白,本站對提供下載的學習資料等不擁有任何權利,版權歸該下載資源的合法擁有者所有。
3、本站保證站內(nèi)提供的所有可下載資源都是按“原樣”提供,本站未做過任何改動;但本網(wǎng)站不保證本站提供的下載資源的準確性、安全性和完整性;同時本網(wǎng)站也不承擔用戶因使用這些下載資源對自己和他人造成任何形式的損失或傷害。
4、未經(jīng)本網(wǎng)站的明確許可,任何人不得大量鏈接本站下載資源;不得復制或仿造本網(wǎng)站。本網(wǎng)站對其自行開發(fā)的或和他人共同開發(fā)的所有內(nèi)容、技術手段和服務擁有全部知識產(chǎn)權,任何人不得侵害或破壞,也不得擅自使用。
我要上傳資料,請點我!
管理工具分類
ISO認證課程講義管理表格合同大全法規(guī)條例營銷資料方案報告說明標準管理戰(zhàn)略商業(yè)計劃書市場分析戰(zhàn)略經(jīng)營策劃方案培訓講義企業(yè)上市采購物流電子商務質(zhì)量管理企業(yè)名錄生產(chǎn)管理金融知識電子書客戶管理企業(yè)文化報告論文項目管理財務資料固定資產(chǎn)人力資源管理制度工作分析績效考核資料面試招聘人才測評崗位管理職業(yè)規(guī)劃KPI績效指標勞資關系薪酬激勵人力資源案例人事表格考勤管理人事制度薪資表格薪資制度招聘面試表格崗位分析員工管理薪酬管理績效管理入職指引薪酬設計績效管理績效管理培訓績效管理方案平衡計分卡績效評估績效考核表格人力資源規(guī)劃安全管理制度經(jīng)營管理制度組織機構(gòu)管理辦公總務管理財務管理制度質(zhì)量管理制度會計管理制度代理連鎖制度銷售管理制度倉庫管理制度CI管理制度廣告策劃制度工程管理制度采購管理制度生產(chǎn)管理制度進出口制度考勤管理制度人事管理制度員工福利制度咨詢診斷制度信息管理制度員工培訓制度辦公室制度人力資源管理企業(yè)培訓績效考核其它
精品推薦
下載排行
- 1社會保障基礎知識(ppt) 16695
- 2安全生產(chǎn)事故案例分析(ppt 16695
- 3行政專員崗位職責 16695
- 4品管部崗位職責與任職要求 16695
- 5員工守則 16695
- 6軟件驗收報告 16695
- 7問卷調(diào)查表(范例) 16695
- 8工資發(fā)放明細表 16695
- 9文件簽收單 16695
- 10跟我學禮儀 16695